New road closures in a Wiltshire town centre will come into effect as a major programme of roadworks at a busy junction moves forward.
Wiltshire Council has outlined traffic management changes as the major project to increase capacity on Longfield Gyratory moves into a new phase.
This phase of the programme will require two significant closures on County Way, between the junction with Dursley Road and the Longfield Gyratory, beginning on Friday, January 23.
The council had initially said this next phase would begin on Thursday, January 22, but have since pushed the start date back one day to allow Wessex Water to finish fixing a burst pipe on Bradley Road.
The council has said the works on the gyratory will improve traffic flow and overall safety around the gyratory, and also boost cycling and walking connections.
Suggested reading:
-
Wildlife Trust abandons wetland project as regeneration in jeopardy
-
Hero saved drowning woman’s life after hearing 'blood curdling scream'
-
Shopping centre owner issues strong statement over car park plan rejection
The next construction phase will require the following closures:
County Way southbound closure, January 23 – February 6
- During this period, no southbound traffic will be permitted to travel from the Longfield Gyratory towards Bradley Road.
However:
- Access from Bradley Road to the gyratory will remain open.
- Access between Dursley Road and Bradley Road will also remain possible.
County Way northbound closure, 9 February – 20 March
- During this stage, vehicles will be unable to travel northbound from Bradley Road or Dursley Road towards the Longfield Gyratory.
- Temporary traffic signals will be installed at the junction of Mortimer Street and Longfield Road to ensure safe vehicle movements out of Mortimer Street.
However:
- Access from the gyratory towards Bradley Road and Dursley Road will remain available.
Work starts on Tesco junction as part of Longfield Gyratory project. (Image: Trevor Porter)
A signed diversion route will be in place throughout both closure periods, supported by advance warning signage positioned around the outskirts of the town to guide drivers to the most appropriate alternative routes.
Cllr Martin Smith, cabinet member for Highways, said: “We apologise for any inconvenience caused by these essential works and recognise that they will cause unavoidable disruption, particularly given the scale of the County Way closures.
“Once complete, these improvements to the gyratory will improve traffic flow and increase capacity to account for the increased number of vehicles that will use the roads in the coming years. They will also upgrade the outdated traffic signals, enhance safety for all road users, and improve pedestrian sand cyclist safety and accessibility to the new Trowbridge leisure centre that is under construction.
“We have taken care to put appropriate diversions and local safety measures in place, and we thank residents, businesses and road users for their continued patience as we deliver long-term improvements for Trowbridge.”