A major A-road through town that has seen a months-long programme of works has fully reopened
The A361 County Way fully reopened to traffic on Thursday, May 28, marking the end of roadworks that have been repeatedly delayed.
Work on the stretch of the A-road north of Longfield Gyratory began in late-January, and was expected to conclude in April.
After the project was delayed due to the discovery of a high-voltage cable under the road surface, Wiltshire Council said it was “really sorry” for the prolonged disruption.
With County Way now open again, the project will move onto its next phase on Bythesea Road to facilitate the new leisure centre.
The council has previously said this will take place during the daytime, using narrow lanes.
County Way when it closed to traffic in January. (Image: Trevor Porter)
Full access to all of our articles online and on the app, fewer adverts, a better reading experience, exclusive competitions and more - all for less than the price of a cup of coffee. ☕️Subscribe now! - https://t.co/t7A1ayW7mR pic.twitter.com/Dk1fvaFm1K
— Wiltshire Times (@wiltshiretimes) April 13, 2026
In their most recent comment on the council apologised for the length of time it had taken to complete the County Way phase, but expressed confidence that the project would deliver long-term benefits.
In late April, Cllr Martin Smith, cabinet member for Highways, said: “When complete, these improvements will deliver lasting benefits for Trowbridge, including better traffic flow, upgraded traffic signals and safer, more accessible routes for pedestrians and cyclists, including those travelling to the new leisure centre.
“I’d like to thank everyone for their continued patience while we work to complete this major scheme.”